ICRA in Healthcare Renovations: What Contractors Must Do
October 17, 2026 · Northlane Enterprises
Construction inside a hospital or clinic carries a risk that ordinary commercial work does not: dust and contaminants can harm patients. An Infection Control Risk Assessment (ICRA) is how healthcare facilities and contractors plan to prevent that.
What an ICRA does
An ICRA looks at two things:
- The type of work, from simple inspections to major demolition
- The patients nearby, from non-clinical areas to the most vulnerable, such as operating rooms and intensive care units
Together, these decide which precautions the contractor must use.
How ICRA 2.0 works
The American Society for Health Care Engineering (ASHE) published ICRA 2.0 as an updated version of the tool. It walks through four steps:
- Classify the project type, from Type A (inspection and non-invasive work) to Type D (major demolition or multi-room renovation)
- Identify the patient risk group, from low to highest
- Find the class of precautions, Class I through Class V, from the matrix
- Review the surrounding areas: above, below and next to the work, for noise, vibration, dust, ventilation and impacts on building systems
What the classes mean on site
In general terms:
- Lower classes cover work that creates little or no dust and needs simple controls.
- Class III adds active dust control, such as HEPA vacuums, plastic containment and sealed doors.
- Class IV adds critical barriers, negative air pressure in the work area and pressure monitoring.
- Class V adds an anteroom and protective coveralls.
Higher-class work typically needs an infection control permit before it starts.
What contractors must do
On an ICRA project, the contractor is responsible for:
- Building barriers as specified, often from floor to the deck above
- Keeping the work area under negative pressure with HEPA-filtered exhaust when required
- Installing pressure monitors on the containment
- Using walk-off mats and cleaning paths
- Following clothing and shoe-cover rules
- Removing debris in covered carts along approved routes
- Not removing barriers until the facility inspects and approves
Training matters
Every worker on site, including subcontractors, must understand the rules. Many facilities require infection control training before workers can enter.
Plan it before you price it
ICRA requirements add time and cost: barriers, air handling equipment, after-hours work and inspections. These should be in the bid from the start, not added as change orders.
Healthcare projects with Northlane Enterprises
Northlane Enterprises plans and manages renovation work for healthcare facilities across Dallas–Fort Worth, coordinating trade partners who follow each facility's infection control requirements. Request a quote to discuss your project.